後龍溪水資源環境觀測及調查計畫(2)-跨域加值整合與方案研究評估--光碟版=Environmental Survey for Water Resources in Houlong River(II) – Assessment of Cross-Field Value-Adding Integration
定價:NT$500
中文摘要
天花湖水庫工程計畫主要為供應苗栗地區之公共給水需求。政府為解決財政困窘,近來推出跨域加值計畫政策,以祈紓解籌措公共建設財源壓力,採取「跨域加值」概念推動公共建設,整合開發方式達到更高的效益成果,「跨域」概念不只跨部會合作,還可以跨縣市、跨產業合作,「加值」係指運用政策整體規劃,創造更高價值。
本研究之目的為就天花湖水庫與周邊產業及資源,作異業結合考量,並對其產生之效益、影響、財務、風險及推動方式等項目,進行有系統之評估。作為天花湖水庫將來進行推動跨域加值方案之參考,爰辦理本計畫研處。
英文摘要
I. Origion of the Project and Content of Work
Tien Hwa Hu Reservoir is an important water resource facility under planning of the government and is off-stream designed. It is located at Towu Township of Miaoli County. Area of the catchment is 693 hectares, and the area of flood zone is 222 hectares.
The recharge of Tien Hwa Hu Reservoir mainly from Dalukaeng River Barrage. Dalukaeng river barrage is 228 meters downstream of Dalukaeng hydrological station, and its’ designed intake flow is 22~25 cms, including 2~5 cms suppling to Chuanlong System. The residual water is delivered to the reservoir by diversion tunnel.
To effectively move the ongoing construction projects forward, financial re-distribution is deemed necessary, and the concept of Cross-field value-adding, which means more active financial integration and feasibility should be incorporated into the public works.
While water resources development plans are able to be combined with urban planning within the area, it will help developing the surrounding areas, build a better connection between construction and development, and maximize benefits of public works.
This project analyzes the feasibilities of environment, finance, risk among the facilites, such as Tien Hwa Hu Reservoir, diversion tunnel and Dalukaeng River Barrage, etc, peripheral industries and other related projects.
II. Basic Information and Analysis of Related Cases
A. Collection and Analysis of Policies Related to Water resources and Cross-field value-adding: For the purpose of implementing water resources plan, this project collects policies, which was posted by government administrations, related to water resources and cross-field value-adding.
B. Collection and Analysis of Policies and Case related to Cross-field value-adding at home and abroad: Water resources are expected to have a newer development according to domestic and foreign policies and case analysis. However, plans need to be drafted accoding to no impact of water supply.
C. Collection and Analysis of plans related to surroundings: In order to make a intergrated value-adding project of Tien Hwa Hu Reservoir across space and time, this project collects plans related to surroundings.
D. Investigation and Analysis of Basic Situation: To promote the contruction of the reservoir, this project will take some interviews with regional administrations for understaning residents’ demands and recommendations.
III. Draft of Cross-Field Value-Adding Project and Feasibility Aessessment
A. Relevance Analysis of Main Project with Cross-Field Value-Adding: This project plans yolk zone and protein zone respectively by investigating its neighboring development and taking interviews with residents.
B. Investigation of principal limiting factor and impact factor:
i. Principal Limiting Factor-Environmentally Sensitive Area, Residents’ Objection in addition to keep water quality and quantity, Cooperation of Government and Private Industries.
ii. Impact Factor-Policies, Environment, Programs.
C. Draft of Cross-Field Value-Adding Project: The cases in this project will be planned under conditions such as suitable terrain slope, local development, etc. The cases do not affect the purpose of construction of the reservoir and do not go against restriction of EIA.
D. Feasibility Analysis of Cross-Field Value-Adding Project: This project will follow the manual of cross-field value-adding in water resources planning, and to assess from 4 factors-the purpose of the water resources development, feasibility of regulations, feasibility of finance and feasibility of carried out. The procedure showned in Abstract Figure 1. Results of the analysis showned in Abstract Table 2.
IV. Assessment of Cross-Field Value-Adding Project
A. Feasibility Analysis of Finance Benefit and Risk Assessment:
i. Feasibility Analysis of Finance Benefit- Finance Benefits of this project result in low correlation to cross-field value-adding project according to result of self-liquidating ratio.
ii. Risk Assessment-Reclassify risks to four types: policies, foundation, ecological and program execution. Proposing orientation about decreasing possibilities of factors of risks after analysised it.
B. Raise of Financial Resources, dispatch of funds, fianancial balancing and responsibilities: This project provides two recommendations about amending laws and financial applications.
C. Feasibility Analysis in promoting Cross-Field Value-Adding Project: The Water Resources Planning Institute will make investigation, planning and cooperation of cross-field value-adding with administrations such as Taiwan Water Corporation, Taiwan Power Company, Taiwan Sugar Corporation and other private industries.
In summary, this project takes consideration of social, financial, environmental benefit and makes policies with cross-sector cooperation trough taking interviews with several local administrations. These projects will be anticipated to satisfy local requirements for the purpose of follow-up construction of Tien Hwa Hu Reservoir, developing water resources and creating ecological environment.
全文描述和摘要
這份報告是「後龍溪水資源環境觀測及調查計畫(2) - 跨域加值整合與方案研究評估」的成果。計畫旨在探討如何透過「跨域加值」概念,為天花湖水庫等水資源開發計畫尋求額外財源並提升效益。
研究內容包含:
* **政策與案例分析:** 蒐集國內外水資源及跨域加值相關政策,並分析國內外成功案例,如鳥嘴潭人工湖、石門水庫等,以汲取經驗。
* **現況調查與方案研擬:** 調查後龍溪流域周邊基本現況、相關計畫及地方需求,並針對水庫影響範圍(蛋黃區)及周邊區域(蛋白區)研擬多項跨域加值方案,涵蓋土地利用、異業結合、環境及社會加值等面向。
* **可行性評估:** 從公益目的、法規、財務及執行等四個面向,評估各項跨域加值方案的可行性,篩選出具潛力的方案。
* **財務效益與風險評估:** 分析納入跨域加值方案後的財務效益,並評估潛在風險,提出因應對策。同時探討財源籌措、資金調度及權責關係。
* **綜合評估與建議:** 提出建立溝通平台、整合跨域資源的建議,期望透過跨域加值,提升水庫計畫的自償率,並兼顧地方發展、生態保育與社會效益,達成多贏局面。
總體而言,本計畫為後龍溪水資源開發計畫提供了一個結合多元效益的發展方向,以期在有限的資源下創造最大價值。
- 作者 /艾奕康工程顧問股份有限公司
- 出版項 /台中市:經濟部水利署水利規劃試驗所 ,105.08
- ISBN /9789860493764 ; 9789860493
- 版本項 /初版
- 分類號 /443.6
點選次數:406
PDF下載次數:8
館藏資訊
| 暫存書單 | 登錄號 | 館藏地 | 年代號 | 狀態 | 借閱到期日 | 分館 |
|---|---|---|---|---|---|---|
| AD005292 | 圖書室B1(中辦) | 201608 | 在館 | 水利署總館 | ||
| FD005374 | 本所圖書室(本所B棟地下1樓圖書室) | 201608 | 在館 | 水利規劃分署 | ||
| FD005375 | 本所圖書室(本所B棟地下1樓圖書室) | 201608 | 在館 | 水利規劃分署 | ||
| FD005376 | 本所圖書室(本所B棟地下1樓圖書室) | 201608 | 在館 | 水利規劃分署 |
loading.....
我要預借
後龍溪水資源環境觀測及調查計畫(2)-跨域加值整合與方案研究評估--光碟版=Environmental Survey for Water Resources in Houlong River(II) – Assessment of Cross-Field Value-Adding Integration
AD005292
保留日期至2025-12-18
後龍溪水資源環境觀測及調查計畫(2)-跨域加值整合與方案研究評估--光碟版=Environmental Survey for Water Resources in Houlong River(II) – Assessment of Cross-Field Value-Adding Integration
FD005374
保留日期至2025-12-18
後龍溪水資源環境觀測及調查計畫(2)-跨域加值整合與方案研究評估--光碟版=Environmental Survey for Water Resources in Houlong River(II) – Assessment of Cross-Field Value-Adding Integration
FD005375
保留日期至2025-12-18
後龍溪水資源環境觀測及調查計畫(2)-跨域加值整合與方案研究評估--光碟版=Environmental Survey for Water Resources in Houlong River(II) – Assessment of Cross-Field Value-Adding Integration
FD005376
保留日期至2025-12-18
依河川
依水庫